Low-Temperature Scanning Probe Laboratory-Completed

Please find the sequential steps undertaken from the initial setup to the successful completion of our scanning probe laboratory.

17TH MAY 2017

Once a meeting room...

19TH JULY 2017

'X' marks the spot...

‍

24 JULY 2017

Start of the structural isolation work

‍

7TH AUGUST 2017

All structural work done, including excavation for the isolation slab, and all destruction of the masonry wall.


‍

‍

14TH SEPTEMBER 2017

New Partition Walls

‍

‍

9TH NOVEMBER 2017

Doors...

‍

‍

6TH APRIL 2018

Fully commissioned LT-STM/MBE/ARPES